暗挖隧道近距离斜下穿既有地铁车站的影响分析
CSTR:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

U213

基金项目:

安徽省自然科学基金资助项目(2008085ME168);安徽省重点研究与开发计划标准化专项基金资助项目(202004h7020002)


Impact Analysis of Underground Tunnels Underpassing Subway Stations at a Close Distance Diagonally
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    为了评估不同加固措施对地表、车站及隧道初期支护位移的控制效果,并验证综合加固方案的工程适用性,以合肥市地铁8号线暗挖隧道近距离斜下穿既有3号线一里井车站为工程背景,采用MIDAS GTS NX有限元软件对无加固、临时仰拱、注浆加固、锚杆及综合加固5种工况进行模拟。研究发现:无加固工况下,地表、车站及初期支护最大沉降分别为21.31, 6.36, 16.21 mm,均超出规范限值。单一加固措施中,临时仰拱通过刚性支撑显著降低了三者沉降,降幅为27.59%, 50.31%, 33.99%;注浆加固通过围岩改良抑制初期支护沉降24.55%,但对地表和车站控制效果有限(降幅小于15%);锚杆作用较弱(降幅小于6%)。综合加固通过“刚性支撑-围岩改良-局部锚固”协同机制,分别将沉降降至13.34, 2.15, 6.93 mm(降幅为36.98%, 66.19%, 57.25%),均满足规范要求。实测数据与模拟结果吻合良好,验证了模型的可靠性及综合加固方案的可行性。

    Abstract:

    In order to evaluate the control effect of different reinforcement measures on the displacement of surface, station and tunnel initial support, and verify the engineering applicability of the comprehensive reinforcement scheme, taking the construction background of the underground tunnel of Hefei Metro Line 8, which underpasses the existing Line 3 Yilijing Station at a close distance diagonally. MIDAS GTS NX finite element software is used to simulate five working conditions: no reinforcement, temporary arch, grouting reinforcement, anchor rod and comprehensive reinforcement. The results indicate that under the unreinforced condition, the maximum settlements of the ground surface, station, and initial support reach 21.31, 6.36, 16.21 mm,respectively,all exceeding the specified limits. Among single reinforcement measures,the temporary inverted arch significantly reduces settlements by 27.59%, 50.31%, 33.99% through rigid support; grouting reinforcement suppressed initial support settlement by 24.55% via surrounding rock improvement but shows limited effectiveness on the ground surface and stations (reductions <15%); bolt reinforcement exhibits minimal impact (reductions <6%). Through the collaborative mechanism of“rigid support surrounding rock improvement local anchoring”, the comprehensive reinforcement reduces the settlement to 13.34, 2.15, 6.93 mm respectively (with a reduction of 36.98%, 66.19%, 57.25%), all of which meet the requirements of the specifications. The measured data and simulation results show close agreement with simulation results, verifying the reliability of the model and the feasibility of the comprehensive reinforcement scheme.

    参考文献
    相似文献
    引证文献
引用本文

晏俊杰,祝 磊,吴天祚.暗挖隧道近距离斜下穿既有地铁车站的影响分析[J].湖南工业大学学报,2026,40(5):10-18.