Abstract:In order to evaluate the control effect of different reinforcement measures on the displacement of surface, station and tunnel initial support, and verify the engineering applicability of the comprehensive reinforcement scheme, taking the construction background of the underground tunnel of Hefei Metro Line 8, which underpasses the existing Line 3 Yilijing Station at a close distance diagonally. MIDAS GTS NX finite element software is used to simulate five working conditions: no reinforcement, temporary arch, grouting reinforcement, anchor rod and comprehensive reinforcement. The results indicate that under the unreinforced condition, the maximum settlements of the ground surface, station, and initial support reach 21.31, 6.36, 16.21 mm,respectively,all exceeding the specified limits. Among single reinforcement measures,the temporary inverted arch significantly reduces settlements by 27.59%, 50.31%, 33.99% through rigid support; grouting reinforcement suppressed initial support settlement by 24.55% via surrounding rock improvement but shows limited effectiveness on the ground surface and stations (reductions <15%); bolt reinforcement exhibits minimal impact (reductions <6%). Through the collaborative mechanism of“rigid support surrounding rock improvement local anchoring”, the comprehensive reinforcement reduces the settlement to 13.34, 2.15, 6.93 mm respectively (with a reduction of 36.98%, 66.19%, 57.25%), all of which meet the requirements of the specifications. The measured data and simulation results show close agreement with simulation results, verifying the reliability of the model and the feasibility of the comprehensive reinforcement scheme.