苏洲坝水电站接入系统稳定性分析
DOI:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

基金项目:


Stability Analysis of the Access System of Suzhou Dam Hydropower Station
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    针对苏洲坝水电站接入攸县电网的问题,给出了3种系统接入方案。方案一,新建苏洲坝水电站接入苏塘35 kV变;方案二,新建苏洲坝水电站接入格子塘35 kV变;方案三,新建苏洲坝水电站T接格苏线。先对3种方案进行潮流计算,得到最佳方案,进而对其进行稳定性分析。数据分析结果显示:相较其他2种方案,方案一(即在苏塘变新接一个间隔)的稳定性最好,同时具有较高的经济效益。

    Abstract:

    Aiming at the problem of Suzhou dam hydropower station access to Youxiang county grid, three access schemes are proposed. The first scheme, newly built Suzhou dam hydropower station is accessed to Sutang 35 kV substation; the second scheme, newly built Suzhou dam hydropower station is accessed to Gezitang 35 kV substation; the third scheme, newly built Suzhou dam hydropower station is T type connection to the two substations; By flow calculation, a more appropriate scheme is chosen and then the stability is analyzed. The data analysis results show that compared with the other two schemes, the first scheme has best stability and higher economic efficiency.

    参考文献
    相似文献
    引证文献
引用本文

王思倩,谭 兮.苏洲坝水电站接入系统稳定性分析[J].湖南工业大学学报,2015,29(3):46-50.