Study on Stress Variation Law of Curved Continuous Rigid Frame Bridge with Asymmetric Cantilever Construction at Different Construction Stages
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    结合工程实例——湖南省长沙市大王山旅游度假区桐溪路景观桥,采用有限元软件Midas/civil,对非对称曲线连续刚构桥在不同施工阶段的应力进行计算与分析,得出非对称曲线连续刚构桥在不同施工阶段的应力变化规律。结果表明,在对称施工阶段中,各截面箱梁顶板和底板的压应力呈现出总体上升的变化趋势;在非对称施工阶段中,各截面箱梁顶板的压应力总体下降,箱梁顶板应力随悬臂长度的增加而减小,而箱梁底板应力随悬臂长度的增加而增大;合拢段在预应力钢束张拉完成后,截面应力增加了2~4倍;前一梁段浇筑后至下一梁段浇筑张拉后的截面顶板压应力相对增加值随梁段数的增加而在一定应力值范围内震荡;前一梁段张拉后至下一梁段浇筑后张拉前的截面顶板应力相对减小值随梁段数的增加在一定应力值范围震荡呈上行变化,而截面底板应力呈下行变化。

    Abstract:

    Based on a case study of the engineering example Tongxi Road Landscape Bridge of Dawangshan tourist resort in Changsha, Hunan Province, a calculation and analysis have been made of the stress of asymmetric curve continuous rigid frame bridge at different construction stages by using the finite element software Midas/civil, thus obtaining the stress variation law of asymmetric curve continuous rigid frame bridge at different construction stages. The results show that at the symmetrical construction stage, the compressive stress of the top and bottom plates of box girder in each section shows an overall upward trend; at the asymmetric construction stage, the compressive stress of the top plate of the box girder decreases as the cantilever length increases, while the stress of the bottom plate of the box girder increases with the increase of the cantilever length, with the section stress of the closure section increasing by 2 ~ 4 times after the completion of the prestressing tendon tensioning. The relative increase value of the compressive stress in the top plate of the section from the pouring of the previous beam segment to the pouring and tensioning of the next beam segment vibrates within a certain stress range with the increase of the number of beam segments; the relative decrease of the section roof stress from the previous beam section after the tensioning to the next beam segment before the tensioning changes in a certain stress range with the increase of the number of beam segments, while the cross-section floor stress changes show a downward trend.

    参考文献
    相似文献
    引证文献
引用本文

杨果林,黎 勇,谭文杰,周伏良.非对称悬臂施工曲线连续刚构桥不同施工阶段应力变化规律研究[J].湖南工业大学学报,2021,35(1):1-8.